Dar es Salaam Urban Transport Improvement Project

خلاصة*

The development objective of Dar Es Salaam Urban Transport Improvement Project for Tanzania is to improve transport mobility, accessibility, safety, and quality of transport service delivery along the selected corridors in Dar es Salaam. This project has three components. 1) The first component is Establishment of the Third and Fourth Phases of the Dar es Salaam Bus Rapid Transit (BRT) System, has the following subcomponents: (a) Establishment of...

.خلاصة المشروع هذه مستمدة من وثيقة التقييم المسبق للمشروع، أو تقرير التقييم المُسبق الذي يعده موظفو البنك، أو وثيقة البرنامج، وقد لا تعكس بدقة الطبيعة الحالية لهذا المشروع. *

نتائج أكثر

هدف التنمية

The Project Development Objective (PDO) is to improve transport mobility, accessibility, safety, and quality of transport service delivery along the selected corridors in Dar es Salaam.

تفاصيل رئيسة

تفاصيل مشروع

  • P150937

  • Active

  • Yonas Mchomvu , Fang Xu

  • United Republic of Tanzania

  • تنزانيا

  • 2016/06/29

  • (حتى تاريخ العرض على مجلس المديرين التنفيذيين)

    2017/03/08

  • 2017/06/13

  • دولار أمريكي 450.80 مليون

  • Tanzania National Roads Agency (TANROADS),Dar Rapid Transit Agency (DART)

  • Eastern and Southern Africa

  • 2017

  • دولار أمريكي 425.00 مليون

  • A

  • غير قابل للتطبيق

  • 2026/04/30

  • No

  • BANK APPROVED

  • 2023/12/18

  • Notes

المالية

خطة التمويل (مليون دولار)

لا تتوفر بيانات.
الممول الارتباطات
IDA Credit 425.00
Borrower/Recipient 25.80

إجمالي تمويل المشروع (بملايين الدولارات)

نوع الأداة البنك الدولي للإنشاء والتعمير/المؤسسة الدولية للتنمية
ارتباط مقدم من البنك الدولي للإنشاء والتعمير غير متاح
ارتباط مقدم من المؤسسة الدولية للتنمية 425.00
ارتباط مقدم من البنك الدولي للإنشاء والتعمير + المؤسسة الدولية للتنمية 425.00
أداة إقراض
مبلغ المنحة غير متاح
التكلفة الكلية للمشروع** 450.80

ملخص عن وضع التمويل المقدم من البنك الدولي (بملايين الدولارات) 2025/04/30

تحميل:
لا تتوفر بيانات.
الممول تاريخ الموافقة تاريخ الإقفال أصل القرض المدفوع من القرض الدفعات الفائدة والرسوم والمصاريف

نشاط مالي تفصيلي في 2025/04/30

تحميل:
لا تتوفر بيانات.
فترة الممول نوع العملية (المبلغ (بالدولار

Footnotes

Ratings

تقديرات التنفيذ

Name Review Date
Financial Management Satisfactory 2024-12-16
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-16
Procurement Moderately Satisfactory 2024-12-16
Progress towards achievement of PDO Moderately Satisfactory 2024-12-16
Project Management Moderately Satisfactory 2024-12-16
Monitoring and Evaluation Moderately Satisfactory 2024-12-16

تقديرات الإنجاز

لا تتوفر بيانات.

تقديرات التقييم المستقل

لا تتوفر بيانات.

إطار النتائج

مؤشرات الأهداف التنموية للمشروع

المؤشرخط الأساسالحاليالمستهدف
  • Percentage of population of Dar es Salaam residents with access to the city center within 60 minutes commuting period by public transport through BRT phase 1, 3, and 4 corridorsالقيمة42.0042.0068.00
    التاريخ2016/12/012018/12/312026/04/30
    تعليق
  • Annual average number of pedestrian fatalities along the BRT phase 1, 3, and 4 corridorsالقيمة114.00114.0075.00
    التاريخ2015/12/312018/12/312026/04/01
    تعليق
  • Average rush hour in-vehicle travel time by public transport passengers from Gongo la Mboto to Kivukoniالقيمة91.0067.0050.00
    التاريخ2016/11/282023/10/202026/04/01
    تعليق
  • Satisfactory rating by users for public transport services along the BRT corridors, disaggregated by gender.القيمة15.0030.0080.00
    التاريخ2016/11/282022/03/242026/04/30
    تعليق
  • Average rush hour in-vehicle travel time by public transport from Tegeta to Kivukoniالقيمة105.0095.0055.00
    التاريخ2016/11/282023/10/202026/04/01
    تعليق
  • Percentage of population of Dar es Salaam residents with access to the city center within 60 minutes commuting period using public transport through BRT phases 1 corridorالقيمة42.0042.0050.00
    التاريخ2016/12/012018/12/312025/01/30
    تعليق
  • Annual average number of pedestrian fatalities along the BRT phase 1 corridorالقيمة33.007.0024.00
    التاريخ2015/12/312021/06/152025/05/30
    تعليق
  • Satisfactory rating by female public transport users of the BRT systemالقيمة10.0052.0080.00
    التاريخ2016/11/282023/10/202026/04/30
    تعليق
  • Average rush hour in-vehicle travel time by articulated freight trucks from Tabata Relini to Mbezi Musuguri through Ubungoالقيمة95.0045.0035.00
    التاريخ2016/11/282023/10/202024/06/28
    تعليق
  • Percentage of population of Dar es Salaam residents with access to the city center in 60 minutes commuting period using public transport through BRT phases 1 and 3 corridorsالقيمة42.0042.0061.00
    التاريخ2016/12/012018/12/312025/12/31
    تعليق
  • Annual average number of pedestrian fatalities along the BRT phase 3 corridorالقيمة35.0035.0021.00
    التاريخ2015/12/312018/12/312026/04/30
    تعليق
  • Annual average number of pedestrian fatalities along the BRT phase 4 corridorالقيمة46.0046.0030.00
    التاريخ2015/12/312018/12/312026/04/30
    تعليق

مؤشرات النتائج المرحلية

المؤشرخط الأساسالحاليالمستهدف
  • Completion of BRT phase 3 infrastructure works by valueالقيمة0.0020.00100.00
    التاريخ2017/02/012023/11/172024/12/31
    تعليق
  • Percentage of completion of the Ubungo flyover and upcountry bus terminal worksالقيمة0.00100.00100.00
    التاريخ2017/01/022023/10/202020/12/30
    تعليق
  • DART agency strengthenedالقيمةNoYesYes
    التاريخ2017/01/022023/10/202024/12/31
    تعليق
  • Completion of BRT phase 4 infrastructure works by valueالقيمة0.000.00100.00
    التاريخ2016/11/282023/10/202025/12/31
    تعليق
  • DUTA or equivalent fully establishedالقيمةNoNoYes
    التاريخ2017/01/022023/10/202026/04/30
    تعليق
  • Average daily passenger ridership for BRT phase 1, 3, and 4 systemالقيمة140.00149.00895.00
    التاريخ2016/11/302021/09/152026/04/30
    تعليق
  • Number of graduate transport professionals received structured professional trainingالقيمة0.00388.00100.00
    التاريخ2017/01/022023/10/202024/12/31
    تعليق
  • Average daily passenger ridership for BRT phase 3القيمة0.000.00395.00
    التاريخ2016/11/302023/12/29
    تعليق
  • Percentage of project supported women graduate transport professionals enrolled in SEAPالقيمة0.000.0050.00
    التاريخ2017/01/022021/12/31
    تعليق
  • System for mapping gender harassment in public transport passengers developed for the BRT systemالقيمةNoNoYes
    التاريخ2017/01/022023/10/202026/04/30
    تعليق
  • Average daily passenger ridership for BRT phase 4القيمة0.000.00168.00
    التاريخ2016/11/302023/12/29
    تعليق
  • Design of pilot TOD schemes completed and PPP tenders launchedالقيمةNoNoYes
    التاريخ2016/11/282023/10/202026/04/30
    تعليق
  • System for citizen feedback on the quality of the operation of the BRT system developedالقيمةNoNoYes
    التاريخ2017/01/022023/10/202024/04/30
    تعليق
  • DART traffic control center establishedالقيمةNoNoYes
    التاريخ2016/11/282023/10/202026/04/30
    تعليق
  • Road safety assessment (including audits) carried out on the BRT corridor with focus on vulnerable road usersالقيمةNoYesYes
    التاريخ2016/12/052023/10/202022/12/30
    تعليق